            Completion of Central to Mid-Levels Escalator and


            Walkway System Refurbishment Project


            中環至半山自動扶梯系統更新項目大功告成





            One of our project highlights of the year is undoubtedly the Central   downtown Hong Kong, the project was highly visible in a unique
            to Mid-Levels Escalator and Walkway System Refurbishment   neighbourhood with diverse stakeholders. We successfully
            which began in March 2018 and was completed in April 2022. A   overcame many technical and other challenges to ensure quality
            four-year project awarded to our Anlev Elevator Group by the   and on-time completion of works and harmonious community
            Transport Department and the Electrical                                relations.
            and Mechanical Services Department,
            the contract is substantial for our lifts                              A key challenge was the narrow worksite
            and escalators business and one of the                                 and various physical constraints
            largest contracts in Anlev’s history.                                  posed by the existing system, such as
                                                                                   the escalator canopies and existing
            Launched in 1993, the 800-metre Central                                structure posts, which could neither be
            to Mid-Levels Escalator and Walkway                                    alternated nor modified. Nevertheless,
            System spans nine streets from                                         we had to work out a solution to
            Queen's Road Central to Conduct Road                                   overcome the challenge. We split up
            and was well beyond its serviceable                                    our equipment into several small
            life by the 2010s. Refurbishment and                                   pieces for hoisting in and assembly at
            modernisation were urgently needed to                                  such a narrow working space.
            uplift its service quality and meet the
            latest safety standards.                                               Another challenge was to deploy truck-
                                                                                   mounted cranes for lifting purposes on
            The project entailed the replacement                                   the neighbourhood’s narrow streets
            including escalators and moving                                        without unduly disputing traffic and
            walkways in 11 phases, commenced                                       pedestrians. With limited data of the
            from  Conduit  Road,  one  phase  at                                   existing equipment during the initial
            a time. Situated at the hilly heart of                                 design stage, thanks to the hard work